Construction Updates

Rosemill - St Ives
Rosemill - St Ives

@ July 2018

Lift shafts set and basement slab now poured.

Expected Completion: Mid 2019

42 Strata Titled Apartments

Developer/Builder: Lane Cove Developments

Architect: Zhinar Architects

Details »
Skyline - Merrylands
Skyline - Merrylands

@ July 2018

Hold up with Council now resolved, Builder being appointed excavation to commence shortly.

Expected Completion : Mid 2019

49 Strata Titled Apartments

Builder: Bradfield Building Group

Architect: Saunders Global

Details »
The William - Granville
The William - Granville

@ July 2018

Crane on-site scaffolding going up.

Expected Completion:  Mid 2019

2 Blocks (Total 28 Strata Titled Apartments)

Developer/Builder: Jasara & Sirus Consolidated

Architect: Zhinar Architects

Details »
Vision - Hornsby
Vision - Hornsby

@ July 2018

Final landscaping and site works underway, valuations to begin early August.

Building Works Completion: Estimated August 2018

Settlement: Estimated September/October 2018

89 Strata Titled Apartments

Builder: Northpoint Construction Group

Architect: Giles Tribe

Details »
Wigmund - Merrylands
Wigmund - Merrylands

@ July 2018

Internal fitout underway.

Expected Completion : End 2018

19 Strata Titled Apartments

Builder: Tudor Constructions

Architect: Design Cubical

Details »
Sixteen - Homebush
Sixteen - Homebush

@ July 2018

Access For Valuations Now

Settlement Estimated : August 2018

65 Strata Titled Apartments

Developer/Builder: Landcon

Architect: Urban Link

Details »